Per the specifications provided by the designing engineer of Buyers Protection Group, Hughes Construction completed the following work on this Finnytown home.
- Installed 15 steel pilasters
- Installed one 3″ adjustable steel column on top of a new 12″x 12″ footer that was 4″ above garage floor
- Excavated along foundation and sealed walls with HLM 5000 and capped with dimple board to facilitate drainage
- Installed two new schedule 40 drain lines which were day-lighted to the street
Once the drainage system was completed, soil was replaced and compacted to minimize settlement.